This  basic tutorial help to know how to Creating Time Schedule in SAP HR – A time schedule defines the timetable of a business event that comprises a number of days, each day consisting of up to three day segments. You can use the time schedule to create a schedule model for business event types or an actual schedule for a business event.

Creating Time Schedule

On the SAP Easy Access screen, in the SAP Standard Menu choose

Human Resources -> Training and Events-> Business Events -> Settings -> Current Settings -> Time Schedule. 

Transaction code: S_AHR_61011844

sap hr creating time schedule 1

Next Step,

sap hr creating time schedule 2

  1. Choose Day segment.
  2. Check whether the list of day segments contains one that you could assign to your schedule.

If there is no day segment to suit you, choose New Entries and enter a key for the new day segment. Assign a

maximum of three time blocks (that do not overlap) to the new day segment. You do so by entering a start

and end time for each one. Save your entries.

The Day Segment screen appears

sap hr creating time schedule 3

Next Step,

sap hr creating time schedule 4

  1. Choose Time schedule.
sap hr creating time schedule 5

Here enter the schedule & Name for e.g “2day for” & “ 2day forenoon”.

  1. Choose Time schedule.
  2. Choose New Entries and enter an ID and a name for the new schedule.
  3. Save your entries.
  4. Choose Day schedules.

sap hr creating time schedule 7

Next Step,

sap hr creating time schedule 8

Next Step,

sap hr creating time schedule 9

The data screen Change Assignment of Day Segments to Day Schedules: Overview appears

On this screen you specify the number of days covered by your schedule.

Online Training Tutorials

  • sap hr interview questionsSAP HR (Human Resource) Interview Questions and AnswersSAP HR /HCM is one of the most widely used modules in SAP. I have written a lot on SAP HR Tutorial and this is a summary post that will work as an index to go through with all of them in […]
  • sap hr create cost items 3SAP HR – How to Create Cost Items?We can explain how to create cost items in this tutorial for beginners explain what is cost items, and it gives a brief understanding of and step by step configuration with settings are […]
  • SAP HR Interview Questions & AnswersTop 15 SAP HR Interview Questions & Answerswe herewith find top SAP HR Interview Questions and Answers for fresher and experienced users, SAP HR Interview Questions and Answers 1) What is internal recruitment? Internal […]
  • SAP HCM Interview QuestionsSAP HR Tutorial – SAP HCM Module Training TutorialsSAP HR Tutorial (HCM Module) - To learn some of the free SAP HCM (Human Capital Management) called as SAP Human Resource (HR) module and tutorials for beginners. SAP Human Capital […]
  • sap hr interview questionsSAP HR Interview Questions and answerswe can list out top SAP HR Interview Questions and Answers for Freshers and professionals to learn more on SAP HR Module. SAP HR (Human Resource), module with SAP which include some of the […]
  • SAP HR (Human Resource Management) ModuleSAP HR (Human Resource Management) Module IntroductionSAP HR (Human Resource Management) system solution is one of the largest modules in the SAP R/3 system which enables the effective management of information about th people within an […]
  • logical database PNPSAP HR Table listSAP Training Tutorials gives the to know ore on the SAP HR tables which frequently using SAP HR Module.The list of SAP Human Resources tables as below, DD01L Domains DD02L SAP […]
  • SAP ecosystemAll about SAP Ecosystem -What it means?SAP ecosystem is a chain of partners, software vendors and others who can contribute to innovation and effectiveness of SAP platform. SAP was struggling for creation of support program for […]